Implementation Status

Activities Progress Status on 30 November 2013

 

Activities

Status

Comments / remaining activities

Geodatabase design under the PostgreSQL system by integrating information that couldn’t be managed by the old system

Realized 

 

Migration ACCESS – PostgreSQL

Realized 

 

Treatment of new data collected by the countries’ teams 

Realized 

 

Integration of data into the new information system

Realized 

 

Training on the installation and configuration of tools: server and client 

Realized 

Workshop in Algiers in January 2013

Development of new features and improvement of the interface

Realized 

 

Training of the three concerned countries’ teams on the use of the SAGESSE Interface

Partially realized 

A two-day workshop was held in Tunis, but the occurrence of technical problems hindered the complete realization of planned activities.

GEOSASS overhaul 

Realized 

Installed at OSS server